Problem:

When creating new tasks in Microsoft Project (MSP) after saving the file back to PPM and re-exporting to MSP, the tasks move to the bottom of the project (or bottom of the summary task if added under a phase/summary task)

Steps to Reproduce:

  1. Create a new project in PPM and add a 4 new tasks to the project 
  2. Export the project to MSP
  3. Insert a new task "Task 5" in between Task 2 and Task 3 so that it shows up as the third task in the plan
  4. Save the project back to PPM
  5. Export the project back to MSP

Expected Results: The tasks remain in the same order (Task 5 displays in between Task 2 and Task 3)
Actual Results: The newly created task (Task 5) shows up at the bottom of the project 

Environment:
This applies to all supported PAS environments for all releases.
Cause:

This is due to a setting in Microsoft Project

Resolution:

Resolution:
1. Open a project that has the issue (or a new project) 
2. Click on the 'View' tab in MSP 
3. Click on the 'Sort' option from the menu then select 'Sort By...' 
4. Change Sort by from 'Unique ID' (if showing for you) to 'ID' 
5. Uncheck the box titled 'Permanently renumber tasks' 
6. Click 'Sort' 
7. Save the current view to the Global.MPT:

  • For custom views:
    • Go to the View tab
    • Click on one of the Views drop down (such as "Gantt Chart")
    • Click "Save View",  select the radio option for 'Update Current View' then click OK.
    • Click 'Yes" to the message prompt that asks if you want to replace the view in the Global.MPT
  • For out of the box views (such as Gantt Chart): 
    • Go to File->Organizer 
    • Click on the View under the right hand column and click Copy to move it to the Global.MPT column 
    • Click 'Yes" to the message prompt that asks if you want to replace the view in the Global.MPT

Please help us improve!

Will this information enable you to resolve your issue?

Please tell us what we can do better.

{{feedbackText.length ? feedbackText.length : '0'}}/255

{{status}}

Not what you were looking for?

Search Again >

Product Information

Support by Product >

Communities

Join a Community >

Chat with CA

Just give us some brief information and we'll connect you to the right CA ExpertCA sales representative.

Our hours of availability are 8AM - 5PM CST.

All Fields Required

connecting

We're matching your request.

Unfortunately, we can't connect you to an agent. If you are not automatically redirected please click here.

  • {{message.agentProfile.name}} will be helping you today.

    View Profile


  • Transfered to {{message.agentProfile.name}}

    {{message.agentProfile.name}} joined the conversation

    {{message.agentProfile.name}} left the conversation

  • Your chat with {{$storage.chatSession.messages[$index - 1].agentProfile.name}} has ended.
    Thank you for your interest in CA.


    Rate Your Chat Experience.

    {{chat.statusMsg}}

agent is typing