In the MSP New Driver, receive a warning message that the resource is assigned outside the original dates of a task, even though dates match what is show in PPM

Document ID:  TEC1506364
Last Modified Date:  06/16/2017
{{active ? 'Hide' : 'Show'}} Technical Document Details

Products

  • CA PPM

Releases

  • CA PPM:Release:15.1

Components

  • CLARITY ON DEMAND INVSTMNTS, PRJCTS, RESOURCES & NPIO MGMT:ODINCL
  • CA PPM SAAS MICROSOFT PROJECT (MSP) INTERNAL ONLY:ODMSP
  • CLARITY PPM INVSTMNTS, PRJCTS, RESOURCES & NPIO MANAGEMENT:PPMINV
  • CA PPM MICROSOFT PROJECT (MSP)INTERNAL ONLY:PPMMSP
Problem:

When opening a project in Microsoft Project (MSP) a warning message is unexectedly generated even though no dates/times have changed for a task or assignment. Message: The resource is assigned outside the original dates for task <Task Name> in project <project name>. The duration of this fixed-duration task will change to accommodate the resource assignment.

Notes:

  • This issue is only reproducible if the task duration is greater than one day. 
  • This message will appear by Microsoft Project design if a Fixed Duration task's duration is increasing to warn the user that the task duration is changing, but in this case, there are no durations being pushed out. 

Steps to reproduce:

1.       Create a new project in PPM

2.       Assign a resource to the project (To add the ETCs automatically to the assignment, allocate the resource at 100% allocation)

3.       Create one task with a 2 day duration and assign the resource to the task

4.       Export the project from PPM to MSP

Expected results: No warning message is displayed.

Actual results: The below warning message is generated even though no dates have changed in the MSP project or the project's xml.

"The resource is assigned outside the original dates for task <Task Name> in project <project name>. The duration of this fixed-duration task will change to accommodate the resource assignment."

Environment:
This issue applies to the MSP New Driver for CA PPM 15.1
Resolution:

This issue is no longer reproducible in 15.1 patch 5 and higher

Please help us improve!

Will this information enable you to resolve your issue?

Please tell us what we can do better.

{{feedbackText.length ? feedbackText.length : '0'}}/255

{{status}}

Not what you were looking for?

Search Again >

Product Information

Support by Product >

Communities

Join a Community >

Chat with CA

Just give us some brief information and we'll connect you to the right CA ExpertCA sales representative.

Our hours of availability are 8AM - 5PM CST.

All Fields Required

connecting

We're matching your request.

Unfortunately, we can't connect you to an agent. If you are not automatically redirected please click here.

  • {{message.agentProfile.name}} will be helping you today.

    View Profile


  • Transfered to {{message.agentProfile.name}}

    {{message.agentProfile.name}} joined the conversation

    {{message.agentProfile.name}} left the conversation

  • Your chat with {{$storage.chatSession.messages[$index - 1].agentProfile.name}} has ended.
    Thank you for your interest in CA.


    Rate Your Chat Experience.

    {{chat.statusMsg}}

agent is typing